Chile
05
September 2024

Horizonte Wind farm starts to produce energy

ENERCON is making significant progress in the construction of Horizonte Wind Farm in the Atacama Desert in Chile. Over thirty wind turbines have been officially put into operation.

Following commissioning of the project in May 2024, over thirty wind turbines have been officially put into operation, boosting the production of energy from the location to enhance the proportion of renewable wind energy in the Chilean energy mix.  

This is primarily because more than 92 percent of the components could meanwhile be delivered to the construction site and are now in the final stage of installation. The ENERCON Team is passionate about solving challenges that come up on site. A good example of this is the APS system and wind-resistant electronic winches for installing blades in windy conditions. This has helped to improve installation plans and boost the completion of WEC installation by the end of the year. Over 100 WECs have been installed to date.

This is even more a convincing performance since official police escorts were not sufficiently available and reliable as we had required, the project was facing a major logistical challenge that would have resulted in significant delays in installation plans. In the interest of the project's success, ENERCON worked tirelessly on a solution and introduced private escorts at the end of 2023. Having been involved in the Horizonte WF since the early beginning, Kay Akanbi, ENERCON’s Project Director, is pleased to report that “Delivery on site (DOS) is expected to be completed about 5 weeks later than the original plan, which is a great achievement compared to the impending 12-month delay as a result of the missing police escorts this time last year.”

Because of its isolated location – two hours away from the closest city for medical assistance, the site has two ambulances and helicopter access available 24/7 in case of emergencies – all HSE topics have been a major focus for ENERCON and our customer Colbún, taking into account the natural surroundings of the location and the involvement of twenty-eight companies operating on site. A recent audit led by both teams showed great performance, reflecting the dedication and effort of ENERCON's HSE Team.

Teams are located throughout an 80 km desert area with daily access to more than 30 wind turbines for work, from installation to energization, thus, complete coordination and management of permits for work are continuously handled across this vast area. Hence, ENERCON and Colbún worked together extensively on all preparatory tasks and evaluations to guarantee a smooth and flawless connection.  

Victor Santiago, Colbun's Project Manager for the development and construction of the Horizonte WF, stated: "Colbún provided the knowledge of the Antofagasta region and Chile as a whole, while ENERCON is the product expert, manufacturing, transporting, installing and operating the WECs. This synergy of expertise was the key to the project's success.” Despite facing challenges, the entire Team remains extremely motivated to maintain the current strong momentum in order to successfully complete this impressive project for ENERCON and our customer Colbún by the end of the year.

Your contact for further questions:

Felix Rehwald

Head of Corporate Communications / Spokesperson

Dreekamp 5
26605 Aurich
Germany

View CV

Contact

This is ENERCON

As a pioneer of wind energy technology and a committed supporter of the energy transition, we have specialised in developing, producing, selling and servicing onshore wind turbines. Pursuing our mission of ‘Energy for the world’, we have been championing sustainable energy generation from onshore wind since 1984. Thanks to our innovative wind turbine technology, high quality standards and many years of experience, we are one of the industry’s leading manufacturers anywhere in the world.

Latest news and topics

News
Luxembourg
25
September 2024

ENERCON turbines with a total capacity of 104 MW for Luxembourg

ENERCON and long-standing customer Soler signed contract during WindEnergy Hamburg

Learn more
News
Global
22
July 2024

Solid growth in order intake in the first half of 2024

Market upswing meets quality product portfolio – ENERCON CCO Uli Schulze Suedhoff in the interview on ENERCONs current performance, strong markets and next steps

View details
Press release
Germany
17
July 2024

Strong partnership: First new wind turbine installed in the Bertkow-Baben repowering project

Twelve modern 5.56 megawatt machines replace 31 old turbines / One of the largest renewal projects in Saxony-Anhalt, Germany

View details
40 years of ENERCON
Global
21
June 2024

Great proximity to the customer and a passion for the cause

What has characterised ENERCON Service since the very beginning?

View details